ES&S has provided professional services supporting planning, design and construction projects for the University of Missouri – Columbia since the founding of the firm in 1954. Our work has been directly for the campus, the UM-System, and as a consultant team member for many of the University’s prime design firms and general contractors. Our list of services has utilized a variety of ES&S’ capabilities with civil and geotechnical engineering, surveying, and a wide variety of construction-support professional services. Below is a list of past projects offering an example of those services:
| Year* | Project | Services |
|---|---|---|
| 2020 | Battle Avenue Medical Building – E St. Charles & Battle Drive (27,000-sf facility, 160-stall parking lot) | BOUND; TOPO; LOC; GEOTECH, SITE, SWQ, City Coord., COMP-SOIL; FOUND; REINF; SPEC, STAKE; WELD |
| 2019 | Memorial Stadium South End Zone Expansion | TOPO; GEOTECH; COMP-SOIL; CONC, FOUND; REINF; SPEC, STAKE; WELD, |
| 2019 | New School of Music Building, Phase I (47,000-sf, 3-story, $24M facility) | TOPO; GEOTECH, LOC; COMP-SOIL; FOUND; REINF; SPEC, STAKE; WELD |
| 2018 | State Historical Society of Missouri HQ & Missouri Studies Center (78,000-sf, 3-story, $38M facility) | BOUND; TOPO; LOC; GEOTECH, COMP-SOIL; FOUND; REINF; SPEC, STAKE; WELD |
| 2018 | MATC Steam Manhole 502 Repairs | COMP-SOIL; CONC |
| 2017 | Discovery Drive Extension | BOUND; TOPO; GEOTECH; RDWY; Sanitary Sewer Design; |
| 2017 | MATC Tower Placement | BOUND; TOPO |
| 2017 | New Mizzou Softball Stadium | BOUND; TOPO; GEOTECH; SITE; COMP-SOIL; SPEC; STAKE; WELD; |
| 2017 | Missouri Orthopaedic Institute, Phase II (87,000-sf, 4-story facility) | TOPO; GEOTECH; COMP-SOIL; FOUND; REINF; SPEC; STAKE, WELD |
| 2016 | Elm Street Utility Upgrades – Steam, Storm Drainage | TOPO; GEOTECH; LOC; Routing & Civil Design |
| 2016 | Tiger Avenue Steam Line Replacement | BOUND; TOPO; LOC; |
| 2016 | Engineering Bldg. – Lafferre Hall, 1935/44 Reconstruction & Renovation | TOPO; GEOTECH; COMP-SOIL; FOUND; REINF; SPEC; STAKE |
| 2015 | Steam Tunnel Repair – Lowery Mall | TOPO; |
| 2015 | Memorial Stadium East Expansion, Luxury Suites, & Tiger Terrace | TOPO; GEOTECH; COMP-SOIL; FOUND; REINF; STAKE; |
| 2015 | Memorial Student Union – North Wing Vertical Addn./Refurbish Steam Line | TOPO; |
| 2015 | MATC to Carrie Frankie Dr. Steam Line | TOPO; LOC; |
| 2015 | Expansion of Discovery Ridge Research Park | SITE; Master Plan Consult; EDA Grant Applic; |
| 2015 | College Avenue Safety Enhancement (CASE) Project | TOPO; EASE; RDWY; STAKE; HAWK Beacons; Stakeholder Outreach; |
| 2014 | Memorial Stadium Expansion, Press Box, North Concourse, Amphitheater | TOPO; GEOTECH; COMP-SOIL; FOUND; REINF; STAKE; |
| 2014 | Traditions Plaza Amphitheater & Memorial | BOUND; TOPO; GEOTECH; SITE; COMP-SOIL; STAKE |
| 2014 | Gateway Signage – Multiple Locations | BOUND; TOPO; GEOTECH; SITE; COMP-SOIL; STAKE; SWQ; |
| 2014 | South Providence Medical Bldg / Park – Phase I (85,000-sf facility, 425-stall parking lot) | BOUND; TOPO; EASE; GEOTECH; SITE; COMP-SOIL; RDWY; SWQ; SPEC; STAKE; Site Master Plan; Trail Design |
| 2014 / 2010 | Replace Steam & Condensate Tunnel – Rollins Street & College Avenue | TOPO; LOC; GEOTECH; COMP-SOIL; REINF; STAKE; |
| 2013 | Chilled Water Line to UPMB | LOC; |
| 2013 | East Campus Chilled Water Plant, Phase II | GEOTECH; FOUND; REINF; COMP-SOIL |
| 2012 | MURR Industrial Building-Install Chill Water Service | TOPO; |
| 2012 | Steam Chase to Clark Hall | BOUND; TOPO; LOC; EASE; GEOTECH; FOUND & REINF; COMP-SOIL |
| 2012 | Hospital Drive Relocation & Traffic Signal | BOUND; TOPO; EASE; GEOTECH; LOC; |
| 2010 | MU-PP Combined Heat & Power Upgrades | BOUND; TOPO; LOC; GEOTECH; FOUND; REINF; STAKE; |
| 2010 | Lathrop Hall Steam & Condensate Lines | TOPO; LOC; GEOTECH; |
| 2010 | Telecom Ductbank Relocation – VA Hospital / Hospital Drive & Virginia | TOPO; LOC; Detail Manhole |
| 2009 | Power Plant Cooling Tower | AS-BLT |
| 2009 | Utility Tunnel -PP to Maryland | FOUND; REINF; LOC; COMP-SOIL; AS-BLT |
| 2009 | Red Campus Chilled Water Lines – 7th & Locust | BOUND; TOPO; LOC; FOUND; COMP-SOIL; REINF; |
| 2009 | Red Campus Chilled Water Lines – 6th & Stewart | BOUND; TOPO; LOC; FOUND; COMP-SOIL; REINF; |
| 2009 | Building Steam/H2O Line Replace – Ellis Library | TOPO; LOC |
| 2009 / 2006 | MURR-Moly 99 Facility – Phase I & II | TOPO; STAKE |
| 2008 | Schurz Hall – Steam Lines | TOPO; LOC |
| 2008 | ABC Laboratory Site @ Discovery Ridge | BOUND; TOPO; GEOTECH; SITE; COMP-SOIL; STAKE |
| 2007 | Steam & Condensate Tunnel – Hitt to Rollins | TOPO; LOC; COMP-SOIL; COMP-SOIL; REINF; Groundwater Study |
| 2007 | Steam & Condensate Tunnel – Conley Road & Fifth Street | TOPO; FOUND |
| 2006 | Steam Tunnel / Utility Corridor – Lafferre Hall Upgrades | TOPO; LOC; |
| 2005 | Chilled Waterline to Telecommunications | TOPO; |
| N/A | Francis Quadrangle Columns – multiple years | Survey to Monitor Movement |
| N/A | Various Parking Garages – Conley Ave., #7, Turner Ave., Hitt St.; University Ave.; | BOUND; TOPO; EASE; GEOTECH; SITE; COMP-SOIL; SPEC; STAKE; WELD; |